  • \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \) \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)\(\newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\) \( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\) \( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\) \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\) \( \newcommand{\Span}{\mathrm{span}}\) \(\newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\) \( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\) \( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\) \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\) \( \newcommand{\Span}{\mathrm{span}}\)\(\newcommand{\AA}{\unicode[.8,0]{x212B}}\)

    Organize the process of repainting all walls of a large lecture hall at a university. The walls are in good condition, so a single coat of pain suffices. The process therefore can be reduced to the following tasks:

    • Make a model of the lecture hall in BIM using direct measurements and photographs
    • Classify wall surfaces and their parts with respect to:
      • Labour (e.g. painting parts narrower than 30 cm are more time consuming)
      • Equipment (e.g. parts higher than 220 cm require scaffolding)
      • Accessibility (e.g. parts behind radiators or other fixed obstacles are hard to reach and therefore also time consuming)
    • Measure the wall surfaces
    • Make cost estimates
    • Make a time schedule in 4D BIM

    Deliverables

    1. Process and information diagrams, accompanied by short explanatory comments
    2. Basic model of the lecture hall in a BIM editor
    3. Schedules for classification, measurement, estimates and scheduling in BIM

    Roles

    If the exercise is a group assignment, consider roles for the following aspects:

    • Process management
    • Information management
    • BIM modelling (two or more people)
    • Analyses in BIM (using schedules – two or more people)

    This page titled 4.2: Exercise I- maintenance is shared under a CC BY-NC-SA 4.0 license and was authored, remixed, and/or curated by Alexander Koutamanis (TU Delft Open Textbooks) via source content that was edited to the style and standards of the LibreTexts platform; a detailed edit history is available upon request.