Skip to main content
Engineering LibreTexts

Glossary

  • Page ID
    123863
  • \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)

    \( \newcommand{\dsum}{\displaystyle\sum\limits} \)

    \( \newcommand{\dint}{\displaystyle\int\limits} \)

    \( \newcommand{\dlim}{\displaystyle\lim\limits} \)

    \( \newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\)

    ( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\)

    \( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)

    \( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\)

    \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)

    \( \newcommand{\Span}{\mathrm{span}}\)

    \( \newcommand{\id}{\mathrm{id}}\)

    \( \newcommand{\Span}{\mathrm{span}}\)

    \( \newcommand{\kernel}{\mathrm{null}\,}\)

    \( \newcommand{\range}{\mathrm{range}\,}\)

    \( \newcommand{\RealPart}{\mathrm{Re}}\)

    \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)

    \( \newcommand{\Argument}{\mathrm{Arg}}\)

    \( \newcommand{\norm}[1]{\| #1 \|}\)

    \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)

    \( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\AA}{\unicode[.8,0]{x212B}}\)

    \( \newcommand{\vectorA}[1]{\vec{#1}}      % arrow\)

    \( \newcommand{\vectorAt}[1]{\vec{\text{#1}}}      % arrow\)

    \( \newcommand{\vectorB}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vectorC}[1]{\textbf{#1}} \)

    \( \newcommand{\vectorD}[1]{\overrightarrow{#1}} \)

    \( \newcommand{\vectorDt}[1]{\overrightarrow{\text{#1}}} \)

    \( \newcommand{\vectE}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash{\mathbf {#1}}}} \)

    \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \(\newcommand{\longvect}{\overrightarrow}\)

    \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)

    \(\newcommand{\avec}{\mathbf a}\) \(\newcommand{\bvec}{\mathbf b}\) \(\newcommand{\cvec}{\mathbf c}\) \(\newcommand{\dvec}{\mathbf d}\) \(\newcommand{\dtil}{\widetilde{\mathbf d}}\) \(\newcommand{\evec}{\mathbf e}\) \(\newcommand{\fvec}{\mathbf f}\) \(\newcommand{\nvec}{\mathbf n}\) \(\newcommand{\pvec}{\mathbf p}\) \(\newcommand{\qvec}{\mathbf q}\) \(\newcommand{\svec}{\mathbf s}\) \(\newcommand{\tvec}{\mathbf t}\) \(\newcommand{\uvec}{\mathbf u}\) \(\newcommand{\vvec}{\mathbf v}\) \(\newcommand{\wvec}{\mathbf w}\) \(\newcommand{\xvec}{\mathbf x}\) \(\newcommand{\yvec}{\mathbf y}\) \(\newcommand{\zvec}{\mathbf z}\) \(\newcommand{\rvec}{\mathbf r}\) \(\newcommand{\mvec}{\mathbf m}\) \(\newcommand{\zerovec}{\mathbf 0}\) \(\newcommand{\onevec}{\mathbf 1}\) \(\newcommand{\real}{\mathbb R}\) \(\newcommand{\twovec}[2]{\left[\begin{array}{r}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\ctwovec}[2]{\left[\begin{array}{c}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\threevec}[3]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\cthreevec}[3]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\fourvec}[4]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\cfourvec}[4]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\fivevec}[5]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\cfivevec}[5]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\mattwo}[4]{\left[\begin{array}{rr}#1 \amp #2 \\ #3 \amp #4 \\ \end{array}\right]}\) \(\newcommand{\laspan}[1]{\text{Span}\{#1\}}\) \(\newcommand{\bcal}{\cal B}\) \(\newcommand{\ccal}{\cal C}\) \(\newcommand{\scal}{\cal S}\) \(\newcommand{\wcal}{\cal W}\) \(\newcommand{\ecal}{\cal E}\) \(\newcommand{\coords}[2]{\left\{#1\right\}_{#2}}\) \(\newcommand{\gray}[1]{\color{gray}{#1}}\) \(\newcommand{\lgray}[1]{\color{lightgray}{#1}}\) \(\newcommand{\rank}{\operatorname{rank}}\) \(\newcommand{\row}{\text{Row}}\) \(\newcommand{\col}{\text{Col}}\) \(\renewcommand{\row}{\text{Row}}\) \(\newcommand{\nul}{\text{Nul}}\) \(\newcommand{\var}{\text{Var}}\) \(\newcommand{\corr}{\text{corr}}\) \(\newcommand{\len}[1]{\left|#1\right|}\) \(\newcommand{\bbar}{\overline{\bvec}}\) \(\newcommand{\bhat}{\widehat{\bvec}}\) \(\newcommand{\bperp}{\bvec^\perp}\) \(\newcommand{\xhat}{\widehat{\xvec}}\) \(\newcommand{\vhat}{\widehat{\vvec}}\) \(\newcommand{\uhat}{\widehat{\uvec}}\) \(\newcommand{\what}{\widehat{\wvec}}\) \(\newcommand{\Sighat}{\widehat{\Sigma}}\) \(\newcommand{\lt}{<}\) \(\newcommand{\gt}{>}\) \(\newcommand{\amp}{&}\) \(\definecolor{fillinmathshade}{gray}{0.9}\)
    Glossary Entries

    Word(s)

    Definition

    100% Rule The principle that the WBS must include all project work and nothing outside the authorized scope.
    Above Target PMP score indicating performance above the minimum passing threshold for a domain.
    Accept A response strategy acknowledging risk without proactive response (for threats or opportunities).
    Activity A specific task derived from WBS work packages that consumes time and resources.
    Actual Cost (AC) The total cost incurred for work completed to date.
    Adaptive Approach An iterative, incremental methodology that delivers value in short cycles, accommodating evolving requirements.
    Agile Manifesto The foundational document establishing agile values: individuals and interactions, working software, customer collaboration, and responding to change.
    Analogous Estimating Using historical data from similar projects to estimate current project costs.
    Appraisal Costs Expenditures to find defects: inspection, testing, audits.
    Aspirational Standards Ethical conduct that practitioners should strive toward as ideals of professional behavior.
    Avoid A threat response strategy that eliminates the risk by changing the project plan.
    Baseline An approved version of scope, schedule, or cost against which performance is measured.
    Bidder Conference A meeting with potential vendors to clarify requirements and answer questions.
    Bottom-Up Estimating Aggregating detailed estimates from individual work packages to create total project cost.
    Burndown Chart A visual display showing remaining work versus time, used to track progress toward sprint or release goals.
    Cause-and-Effect Diagram A tool (also called Ishikawa or fishbone) for systematically exploring potential causes of quality problems.
    CCR (Continuing Certification Requirements) PMI’s program requiring credential holders to earn PDUs to maintain certification.
    Change Control Board (CCB) A group with authority to review and approve or reject change requests.
    Claims Administration Managing contractual claims and disputes between buyer and seller.
    Communications Management Plan A document specifying what information will be shared, with whom, how often, and through what methods.
    Confidentiality Protecting sensitive information from inappropriate disclosure.
    Configuration Management The practice of maintaining version control and documentation integrity for project artifacts.
    Conflict of Interest A situation where personal interests could compromise professional judgment.
    Conflict Resolution The process of addressing and resolving stakeholder disagreements constructively.
    Contingency Reserve Budget allocated for identified risks and known uncertainties; part of the cost baseline.
    Continuous Improvement An ongoing effort to enhance processes, products, or services through incremental changes. / Systematic ongoing effort to enhance processes and outcomes (Kaizen, TQM, Six Sigma, retrospectives).
    Contract Change Control Processes for evaluating, approving, and documenting contract modifications.
    Control Chart A tool for monitoring process performance over time and distinguishing normal variation from special causes.
    Cost Baseline The approved, time-phased budget against which cost performance is measured.
    Cost Management Plan A document defining how project costs will be estimated, budgeted, monitored, and controlled.
    Cost of Quality (CoQ) The total cost of conformance (prevention + appraisal) and non-conformance (internal + external failure).
    Cost Performance Index (CPI) EV divided by AC; values below 1.0 indicate cost inefficiency.
    Cost Plus Award Fee (CPAF) A cost-reimbursable contract with fees based on subjective performance evaluation.
    Cost Plus Fixed Fee (CPFF) A cost-reimbursable contract with a fixed fee; buyer bears cost risk.
    Cost Plus Incentive Fee (CPIF) A cost-reimbursable contract with incentives tied to performance targets.
    Cost Variance (CV) EV minus AC; negative values indicate over budget.
    Crashing Adding resources to critical path activities to reduce duration, increasing cost.
    Critical Path The longest sequence of dependent activities that determines minimum project duration.
    Daily Stand-up A brief daily meeting (15 minutes) for team synchronization: what was done, what’s planned, what impediments exist.
    Digital Badge Electronic credential that can be shared on social media and professional profiles.
    Direct and Manage Project Work The process of leading execution of planned activities to produce deliverables.
    Direct Costs Costs directly attributable to project work, such as labor, materials, and equipment.
    Disclosure Revealing information (such as conflicts of interest) that stakeholders have a right to know.
    Earned Value (EV) The authorized budget for work actually completed, measuring accomplished value.
    Emotional Intelligence (EQ) The capacity to recognize, understand, and manage one’s own emotions and influence others’ emotions.
    Enhance An opportunity response strategy increasing the probability or impact of the positive risk.
    Estimate at Completion (EAC) Projected total cost at project completion based on current performance.
    Ethical Decision-Making Framework A structured approach to analyzing dilemmas: identify stakeholders, clarify the dilemma, generate options, evaluate consequences, apply principles, seek counsel, decide and document.
    Ethical Dilemma A situation where ethical principles conflict or guidelines are unclear, requiring judgment.
    Expected Monetary Value (EMV) A quantitative technique calculating risk value as probability multiplied by impact.
    Explicit Knowledge Knowledge that can be documented and easily shared (processes, specifications, lessons learned).
    Exploit An opportunity response strategy ensuring the positive risk is realized.
    Extrinsic Motivation Drive based on external rewards such as money, status, or recognition.
    Failure Costs Costs from defects that occur: rework (internal) and warranty/returns (external).
    Fairness Making impartial decisions based on objective criteria without favoritism or bias.
    Fast-Tracking Overlapping activities that would normally be sequential, increasing risk.
    Feedback Loop A mechanism for collecting and responding to stakeholder input.
    Finish-to-Start (FS) A dependency where the successor cannot start until the predecessor finishes.
    Firm Fixed-Price (FFP) A contract with a set total price; seller bears cost risk.
    Fixed Price with Incentive Fee (FPIF) A fixed-price contract with incentives for cost, schedule, or performance targets.
    Float (Slack) The amount of time an activity can be delayed without affecting project completion.
    Framework A structured set of practices and guidelines for managing projects, providing a consistent approach without dictating exact methods.
    Giving Back PDUs PDUs earned through knowledge sharing, volunteering, mentoring, or content creation.
    Governance The framework of authority, accountability, and oversight guiding project execution.
    Grade A category or rank given to entities with the same functional use but different technical characteristics.
    Histogram A tool displaying the distribution of quality measurements to reveal patterns and variation.
    Honesty Communicating truthfully, reporting accurately, and acting with integrity.
    Hybrid Approach A blend of predictive and adaptive methods tailored to a project’s specific needs. / A methodology combining elements of agile and predictive approaches based on project needs.
    Hybrid Communication Combining agile interaction with formal documentation and reporting to satisfy diverse stakeholder needs.
    Indirect Costs Overhead and support costs allocated to the project, such as facilities and administrative expenses.
    Information Radiator A visible display of project information that stakeholders can easily access (e.g., task boards, dashboards). / A visible display (physical or digital) that keeps project information accessible to all stakeholders.
    Integrated Change Control The formal process of reviewing, evaluating, and approving or rejecting change requests.
    Integration Management The practice of coordinating all project elements to ensure they work together as a unified whole.
    Interactive Communication Real-time, bidirectional information exchange (e.g., meetings, video calls).
    Intrinsic Motivation Drive that comes from internal satisfaction, purpose, mastery, and autonomy.
    Kanban An agile approach emphasizing continuous flow, visual boards, and work-in-progress limits.
    Key Performance Indicator (KPI) A measurable value that indicates progress toward a goal.
    Knowledge Area A category of project management processes defined by PMI (e.g., Scope, Schedule, Cost, Risk).
    Knowledge Management The practice of capturing, sharing, and leveraging both explicit and tacit knowledge.
    Lag Time A delay between the predecessor and successor activities.
    Lead Time An acceleration of the successor activity, allowing it to start before the predecessor finishes.
    Lessons Learned Documentation of what worked well, what could be improved, and what should be avoided in future projects.
    Life Cycle The sequence of phases a project passes through from initiation to closure.
    Make-or-Buy Analysis A decision process evaluating whether to produce internally or acquire externally.
    Management Reserve Budget for unforeseen circumstances; not part of the cost baseline, requires higher approval to access.
    Mandatory Standards Ethical requirements that could result in disciplinary action if violated.
    Mark-and-Review Exam function allowing candidates to flag questions for later review.
    Mentorship Guidance provided by an experienced individual to support another’s professional development.
    Milestone A significant point or event in the project with zero duration.
    Mitigate A threat response strategy that reduces the probability or impact of the risk.
    Monte Carlo Simulation A quantitative technique modeling project outcomes across thousands of scenarios.
    Online Proctoring Remote exam delivery monitored via webcam and screen sharing.
    Operations Ongoing, repetitive activities that sustain the organization’s core business functions.
    Opportunity A positive risk that could benefit project objectives if it occurs.
    Organizational Structure The framework defining authority, communication flow, and resource control within an organization.
    Parametric Estimating Using mathematical relationships between project variables and costs to calculate estimates.
    Pareto Chart A tool for prioritizing quality issues by ranking defect types by frequency or impact.
    PDU (Professional Development Unit) Unit of measurement for learning and professional service activities required for certification maintenance.
    Pearson VUE The test administration company that delivers PMP and CAPM exams at testing centers and online.
    PERT Formula Expected duration = (Optimistic + 4×Most Likely + Pessimistic) ÷ 6.
    PfMP Portfolio Management Professional, credential for strategic portfolio management.
    PgMP Program Management Professional, advanced credential for managing multiple related projects.
    Planned Value (PV) The authorized budget for work scheduled to be completed by a given date.
    PMI Code of Ethics and Professional Conduct The framework defining ethical principles and standards for PMI members and credential holders.
    PMI Talent Triangle Framework for professional development covering technical, leadership, and strategic/business management skills.
    PMI-ACP PMI Agile Certified Practitioner, credential demonstrating agile expertise.
    PMO (Project Management Office) An organizational body that standardizes project governance, provides support, and maintains best practices.
    Portfolio A collection of programs, projects, and operational work selected and managed to achieve strategic objectives.
    Power-Interest Grid A tool to categorize stakeholders based on their authority/influence and level of interest in the project.
    Precedence Diagramming Method (PDM) A technique for creating network diagrams showing activity dependencies.
    Predictive Approach A methodology that defines scope, schedule, and cost early in the life cycle, suitable for stable requirements.
    Prevention Costs Investments to prevent defects: training, quality planning, design reviews.
    Probability-Impact Matrix A tool for prioritizing risks based on their probability of occurrence and potential impact.
    Process Group A logical cluster of related project management processes (Initiating, Planning, Executing, Monitoring & Controlling, Closing).
    Procurement Audit A structured review of procurement processes to identify successes and lessons learned.
    Procurement Management Plan A document defining how procurements will be planned, executed, and controlled.
    Product Backlog An ordered list of all work to be done on a product, owned by the product owner. / An ordered list of everything needed in the product, owned and prioritized by the product owner.
    Product Owner The role accountable for maximizing product value through backlog prioritization and stakeholder synthesis. / The person responsible for maximizing product value by managing the product backlog and representing stakeholder interests.
    Product Scope The features, functions, and characteristics of the deliverable.
    Professional Development Ongoing obligation to maintain competence and improve capabilities.
    Program A collection of related projects managed in a coordinated way to obtain benefits not available from managing them individually.
    Progressive Elaboration The process of developing a project in increments as more information becomes available.
    Project A temporary endeavor undertaken to create a unique product, service, or result.
    Project Charter A document that formally authorizes a project and grants the project manager authority to apply resources.
    Project Closure The formal process of completing all activities, obtaining acceptance, and transitioning deliverables.
    Project Management Plan The comprehensive, integrated collection of subsidiary plans that guides project execution and control.
    Project Scope The work that must be performed to deliver the product with its specified features.
    Psychological Safety An environment where team members feel safe to take risks, ask questions, and admit mistakes without fear.
    Pull Communication Information made available for stakeholders to access when needed (e.g., portals, dashboards).
    Push Communication One-way information delivery sent to recipients (e.g., emails, reports).
    Quality The degree to which deliverables fulfill requirements and meet stakeholder expectations.
    Quality Assurance (QA) Proactive process-focused activities to prevent defects and ensure process effectiveness.
    Quality Control (QC) Reactive product-focused activities to inspect, test, and verify deliverables meet standards.
    Quality Management Plan A document defining quality standards, metrics, roles, and processes for the project.
    RACI Matrix A responsibility assignment tool defining who is Responsible, Accountable, Consulted, and Informed for each task.
    Request for Proposal (RFP) A solicitation document requesting vendor proposals for defined requirements.
    Requirements Traceability Matrix A tool linking requirements to their origins and to the deliverables that satisfy them.
    Residual Risk The risk remaining after risk responses have been implemented.
    Resource Breakdown Structure (RBS) A hierarchical representation of resources organized by category and type.
    Resource Leveling Adjusting the schedule to address resource over-allocation, often extending the timeline. / Adjusting the schedule to resolve resource overallocation, often extending duration.
    Resource Smoothing Adjusting activities within available float to reduce resource demand peaks without changing the critical path.
    Respect Valuing others, listening actively, and treating all stakeholders with dignity regardless of role or status.
    Responsibility Owning decisions and their consequences, fulfilling commitments, and acting in the project’s best interest.
    Retrospective A structured team reflection to identify improvements for future work. / An end-of-sprint ceremony where the team reflects on process and identifies improvements.
    Risk An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives.
    Risk Audit An examination of the effectiveness of risk responses and the risk management process.
    Risk Management Plan A document defining how risk management activities will be structured and performed.
    Risk Register A document listing identified risks, their assessments, response strategies, and owners.
    Risk Trigger An early warning sign or condition indicating that a risk is about to occur or has occurred.
    Root Cause Analysis Techniques for identifying the fundamental reason for a problem.
    Salience Model A stakeholder classification model based on power, legitimacy, and urgency.
    Schedule Management Plan A document defining how the schedule will be developed, monitored, and controlled.
    Schedule Performance Index (SPI) Earned Value divided by Planned Value; values below 1.0 indicate inefficiency.
    Schedule Variance (SV) Earned Value minus Planned Value; negative values indicate behind schedule.
    Scope Baseline The approved version of the scope statement, WBS, and WBS dictionary against which changes are measured.
    Scope Control The process of monitoring scope status and managing changes to the scope baseline.
    Scope Creep Uncontrolled expansion of project scope without corresponding adjustments to time, cost, or resources.
    Scope Management The processes that ensure the project includes all required work, and only required work.
    Scope Statement A detailed description of project deliverables, acceptance criteria, exclusions, constraints, and assumptions.
    Scope Validation The process of obtaining formal stakeholder acceptance of completed deliverables.
    Scrum An agile framework using time-boxed sprints, defined roles (product owner, scrum master, development team), and ceremonies.
    Scrum Master The servant leader who facilitates Scrum ceremonies, removes impediments, and coaches the team on agile practices.
    Secondary Risk A new risk that arises as a direct result of implementing a risk response.
    Self-Organizing Team A team that manages its own work allocation, sequencing, and problem-solving with minimal direction. / A team that manages its own work allocation, sequencing, and problem-solving within provided constraints.
    Servant Leadership A leadership philosophy focused on serving the team’s needs to enable their success. / A leadership philosophy where the leader’s primary role is serving the team by removing obstacles and enabling success.
    Source Selection Criteria Predetermined factors and weights used to evaluate vendor proposals.
    Sprint A time-boxed iteration (typically 2-4 weeks) during which a potentially shippable product increment is created.
    Sprint Backlog The set of product backlog items selected for a sprint plus the plan for delivering them.
    Sprint Review An agile ceremony at the end of a sprint to inspect the product increment and gather stakeholder feedback. / An end-of-sprint ceremony where the team demonstrates the increment and gathers stakeholder feedback.
    Stakeholder Any individual, group, or organization with an interest in or influence over a project.
    Stakeholder Register A document capturing stakeholder information, including names, roles, influence, and interests.
    Standard An agreed-upon set of rules, guidelines, or characteristics established by an authority to ensure consistency and quality.
    Statement of Work (SOW) A document specifying deliverables, acceptance criteria, and performance standards.
    Succession Planning Preparing for leadership and role continuity when key team members transition.
    Tacit Knowledge Knowledge based on personal experience and intuition that is difficult to document.
    Tailoring Customizing standard practices to suit a specific project’s context and needs.
    Team Development (Tuckman Model) The stages teams progress through: forming, storming, norming, performing, and adjourning.
    Threat A negative risk that could harm project objectives if it occurs.
    Three-Point Estimate An estimation technique using optimistic, pessimistic, and most likely values.
    Three-Point Estimating Using optimistic, pessimistic, and most likely values to calculate expected cost with uncertainty.
    Time and Materials (T&M) A hybrid contract paying hourly rates plus material costs; used when scope is undefined.
    Transfer A threat response strategy that shifts risk impact to a third party.
    Transparency Open communication that gives stakeholders the information they need for informed decisions.
    Triple Constraint The interrelationship of scope, time, and cost, changes to one affect the others.
    Trust Building Establishing credibility through consistent transparency, reliability, and mutual respect.
    User Story An agile requirements format describing functionality from the user’s perspective: As a [user], I want [function] so that [benefit].
    Validation Confirming that deliverables satisfy stakeholder needs (“Did we build the right thing?”).
    Variance at Completion (VAC) BAC minus EAC; the projected budget variance at project completion.
    Velocity An agile metric measuring the amount of work a team completes per iteration. / A measure of the amount of work a team completes in a sprint, used for forecasting future capacity.
    Verification Confirming that deliverables conform to specifications (“Did we build it right?”).
    WBS Dictionary A document providing detailed descriptions of each WBS element including scope, deliverables, and acceptance criteria.
    Work Breakdown Structure (WBS) A hierarchical decomposition of total project work into smaller, manageable components.
    Work Package The lowest level of the WBS, a component small enough to be estimated, assigned, and tracked.